Project Summary

  • The project consists of replacing the existing 19.88-G.26 bridge, which consists of four CMP’s at 84 inch along on Canyon Creek Drive.
  • This also includes improving Canyon Creek Drive by widening the asphalt and shoulder along the road and all related
    • Road work
    • Storm water control
    • Irrigation control
    • Utility coordination
    • Soil disturbance mitigation

Bid Closed

January 17, 2023

Apparent Low Bidder

  • United Companies
  • $1,440,336.47

Advertisement, Attachments, Bid Tabulation